The largest public project underway in our area is the Kuykendahl Underpass by TxDOT. Other agencies also have projects underway. Check back to this page often for updated info and links to projects in the area.
TxDOT Project Information
Estimated Construction Start - October, 2005 Estimated Completion - Second to third quater 2008 Estimated Construction Cost - $15,000,000 Extent of streets to be improved: FM 1960 will be improved almost 0.2 mile east and west of Kuykendahl. Kuykendahl will be improved from approximately 0.3 mile south to almost 0.4 mile north of FM 1960. Kuykendahl at FM 1960
|